Objektverhalten bei Routenstilllegung

Mit der Location Referencing-Lizenz verfügbar.

Die Stilllegung von Routen hat je nach konfiguriertem Objektverhalten für die einzelnen Objekt-Layer unterschiedliche Auswirkungen auf Objekte.

Hinweis:

Events are not updated until the Apply Event Behaviors tool is applied after route edits. If you are using conflict prevention, you are prompted to run Apply Event Behaviors before posting can be completed.

Hinweis:

When recalibrate downstream is chosen for an LRS route edit, the configured calibrate event behavior is applied to downstream sections.

The following sections detail the results of executing the Apply Event Behaviors tool on event features after a corresponding route edit.

Route retirement scenario

The following retirement scenario involves one route and three events. The retirement (depicted with a dashed line) starts in Event1, completely spans Event2, and ends in Event3.

Before retirement

Stay Put behavior

The geographic location of the event outside of the retire region is preserved; the measures can change. The event can also split if it crosses the retire region. Portions of the reassign region are retired.

Stay Put behavior

Move behavior

The measures and route of the event are maintained; the geographic location can change.

Move behavior

Retire behavior

The geographic location and measure of the event are preserved; the event is retired. Events intersecting the retire region are retired.

Retire behavior

Upstream and downstream sections

Route editing impacts upstream and downstream sections differently.

The following diagram shows the upstream and downstream sections for the route retirement scenario:

Upstream and downstream sections

The following table details how the retirement editing activity impacts upstream and downstream events according to the configured event behavior:

Behavior Events upstream Events intersecting Events downstream

Stay Put

No action.

Retire event; line events crossing the edit region are split and the original event retired.

If route calibration is changed, the recalibrate event behavior is applied; otherwise, no action.

Move

Shape regenerated, if needed, to new location of route measures.

Shape regenerated to new location of route measures.

If route calibration is changed, the recalibrate event behavior is applied; otherwise, no action.

Retire

No action.

Retire event; line events crossing edit region are not split.

If route calibration is changed, the recalibrate event behavior is applied; otherwise, no action.

Hinweis:
  • Point events follow the same behavior as line events but don't need to be split.
  • If the Recalibrate route downstream option is chosen, calibrate route event behaviors are applied to the events downstream of the edited portion of the route.
  • The network can contain events that span multiple routes in a line network. In this case, the behaviors are still applied in the same manner.
  • Since the LRS is time aware, edit activities—such as retiring a route—time slice routes and events.

Detailed behavior results

The following sections detail how event behavior rules are enforced when a route is retired.

Stay Put behavior

The route is active from 1/1/2000, and if the retirement is set to occur on 1/1/2005 and Recalibrate route downstream is not chosen, this has the following effects:

  • Event1 is represented by two time slices. There is a time slice from 1/1/2000 to 1/1/2005, with the original measures from 0 to 20, and a time slice from 1/1/2005 to <Null>, with measures from 0 to 15, that stay the same location geographically.
  • Event2 retires to maintain geographic location.
  • Event3 is represented by two time slices. There is a time slice from 1/1/2000 to 1/1/2005, with the original measures from 30 to 45, and a time slice from 1/1/2005 to <Null>, with measures from 35 to 45, that stay the same geographically.

Before Stay Put event behavior

The following diagram provides details about the route before retirement:

Before Stay Put event behavior

The following table provides details about the events before retirement:

EventRoute NameFrom DateTo DateFrom MeasureTo Measure

Event1

Route1

1/1/2000

<Null>

0

20

Event2

Route1

1/1/2000

<Null>

20

30

Event3

Route1

1/1/2000

<Null>

30

45

After Stay Put event behavior

The following diagram provides details about the route after retirement:

After Stay Put event behavior

The following table provides details about the events after retirement when Stay Put is the configured event behavior:

EventRoute NameFrom DateTo DateFrom MeasureTo MeasureLocation Error

Event1

Route1

1/1/2000

1/1/2005

0

20

No Error

Event1

Route1

1/1/2005

<Null>

0

15

No Error

Event3

Route1

1/1/2000

1/1/2005

30

45

No Error

Event3

Route1

1/1/2005

<Null>

35

45

No Error

Move behavior

The route is active from 1/1/2000, and if the retirement is set to occur on 1/1/2005 and Recalibrate route downstream is not chosen, this has the following effects:

  • Event1 is represented by two time slices. There is a time slice from 1/1/2000 to 1/1/2005 and a time slice from 1/1/2005 to <Null>, both with the original measures from 0 to 20. This new time slice will only partially locate since the event time slice has measures from 0 to 20, but the underlying route time slice only has measures from 0 to 15 and 35 to 55, with a physical gap created due to retirement.
  • Event2 is represented by two time slices. There is a time slice from 1/1/2000 to 1/1/2005 and a time slice from 1/1/2005 to <Null>, both with the measures from 20 to 30. This new time slice will not locate since the event time slice has measures from 20 to 30, but the underlying route does not have a route with those measures.
  • Event3 is represented by two time slices. There is a time slice from 1/1/2000 to 1/1/2005 and a time slice from 1/1/2005 to <Null>, both with the original measures 30 to 45. This new time slice only partially locates since the event time slice has measures from 30 to 45, but the underlying route time slice only has measures from 0 to 15 and 35 to 55, with a physical gap created due to retirement.

Before Move event behavior

The following diagram provides details about the route before retirement:

Before Move event behavior

The following table provides details about the events before retirement:

EventRoute NameFrom DateTo DateFrom MeasureTo Measure

Event1

Route1

1/1/2000

<Null>

0

20

Event2

Route1

1/1/2000

<Null>

20

30

Event3

Route1

1/1/2000

<Null>

30

45

After Move event behavior

The following diagram provides details about the route after retirement:

After Move event behavior

The following table provides details about the events after retirement when Move is the configured event behavior:

EventRoute NameFrom DateTo DateFrom MeasureTo MeasureLocation Error

Event1

Route1

1/1/2000

1/1/2005

0

20

No Error

Event1

Route1

1/1/2005

<Null>

0

20

Partial match for the To measure

Event3

Route1

1/1/2000

1/1/2005

30

45

No Error

Event3

Route1

1/1/2005

<Null>

30

45

Partial match for the From measure

Retire behavior

The route is active from 1/1/2000, and if the retirement is set to occur on 1/1/2005 and Recalibrate route downstream is not chosen, this has the following effects:

  • Event1 retires since it intersects the retired region.
  • Event2 retires since it is completely inside the retired region.
  • Event3 retires since it intersects the retired region.

Before Retire event behavior

The following diagram provides details about the route before retirement:

Before Retire event behavior

The following table provides details about the events before retirement:

EventRoute NameFrom DateTo DateFrom MeasureTo Measure

Event1

Route1

1/1/2000

<Null>

0

20

Event2

Route1

1/1/2000

<Null>

20

30

Event3

Route1

1/1/2000

<Null>

30

45

After Retire event behavior

The following diagram provides details about the route after retirement:

After Retire event behavior

The following table provides details about the events after retirement when Retire is the configured event behavior:

EventRoute NameFrom DateTo DateFrom MeasureTo MeasureLocation Error

Event1

Route1

1/1/2000

1/1/2005

0

20

No Error

Event2

Route1

1/1/2000

1/1/2005

20

30

No Error

Event3

Route1

1/1/2000

1/1/2005

30

45

No Error

Detailliertes Verhalten bei Routen in einem Liniennetzwerk mit routenübergreifenden Objekten

Verhalten "Verbleiben"

Dieses Stilllegungsszenario umfasst vier Routen auf einer Linie in einem Liniennetzwerk und zwei Objekte. Route3 wird stillgelegt. Die stillgelegte Route (dargestellt durch eine gepunktete Linie) wirkt sich auf Objekt1 und Objekt2 aus.

Die Routen sind ab dem 1.1.2000 aktiv. Wenn die Stilllegung auf den 1.1.2005 festgelegt ist und Route nachgelagert neu kalibrieren deaktiviert ist, hat dies folgende Auswirkungen:

  • Objekt1 wird durch zwei Zeitintervalle dargestellt. Es gibt ein Zeitintervall vom 1.1.2000 bis zum 1.1.2005 mit den ursprünglichen Messwerten 0 bis 30 auf Route1 und Route3 und ein Zeitintervall vom 1.1.2005 bis <null> mit den Messwerten 0 auf Route1 bis 22 auf Route2, da die geographische Position gleich bleibt. Der Teil des Objekts auf Route3 wird stillgelegt, da es keine Route mehr gibt, auf der der Teil des Objekt-Shapes erstellt werden kann.
  • Objekt2 wird durch zwei Zeitintervalle dargestellt. Es gibt ein Zeitintervall vom 1.1.2000 bis zum 1.1.2005 mit den ursprünglichen Messwerten 30 auf Route3 bis 48 auf Route4 und ein Zeitintervall vom 1.1.2005 bis <null> mit den Messwerten 38 auf Route4 bis 48 auf Route4, da die geographische Position gleich bleibt. Der Teil des Objekts auf Route3 wird stillgelegt, da es keine Route mehr gibt, auf der der Teil des Objekt-Shapes erstellt werden kann.

Vor dem Objektverhalten "Verbleiben"

The following table provides details about the events before retirement:

Vor dem Objektverhalten "Verbleiben"

Ereignis-IDStartdatumEnddatumVon-RouteIDBis-Routen-IDVon-MesswertBis-Messwert

Event1

01.01.2000

<NULL>

Route1

Route3

0

30

Event2

01.01.2000

<NULL>

Route3

Route4

30

48

Nach dem Objektverhalten "Verbleiben"

The following diagram provides details about the route after retirement:

Nach dem Objektverhalten "Verbleiben"

Ereignis-IDStartdatumEnddatumVon-RouteIDBis-Routen-IDVon-MesswertBis-MesswertPositionsfehler

Event1

01.01.2000

01.01.2005

Route1

Route3

0

30

Kein Fehler

Event1

01.01.2005

<NULL>

Route1

Route2

0

22

Kein Fehler

Event2

01.01.2000

01.01.2005

Route3

Route4

30

48

Kein Fehler

Event2

01.01.2005

<NULL>

Route4

Route4

38

48

Kein Fehler

Verhalten "Verschieben"

Die Routen sind ab dem 1.1.2000 aktiv. Wenn die Stilllegung auf den 1.1.2005 festgelegt ist und Route nachgelagert neu kalibrieren deaktiviert ist, hat dies folgende Auswirkungen:

  • Objekt1 wird durch zwei Zeitintervalle dargestellt. Es gibt ein Zeitintervall vom 1.1.2000 bis zum 1.1.2005 und ein Zeitintervall vom 1.1.2005 bis <null>, beide mit den ursprünglichen Messwerten 0 auf Route1 bis 30 auf Route3. Dieses neue Zeitintervall wird nur teilweise verortet, da das Objektzeitintervall die Messwerte 0 bis 30 auf Route1 bis Route3 aufweist, aber Route3 stillgelegt wurde, sodass es an der Position keine Route mehr zum Erstellen eines Shapes gibt.
  • Objekt2 wird durch zwei Zeitintervalle dargestellt. Es gibt ein Zeitintervall vom 1.1.2000 bis zum 1.1.2005 und ein Zeitintervall vom 1.1.2005 bis <null>, beide mit den Messwerten 30 auf Route3 bis 48 auf Route4. Dieses neue Zeitintervall wird nicht verortet, da das Objektzeitintervall die Messwerte 30 bis 48 auf Route3 bis Route4 aufweist, aber Route3 stillgelegt wurde, sodass es an der Position keine Route mehr zum Erstellen eines Shapes gibt.

Vor dem Objektverhalten "Verschieben"

The following table provides details about the events before retirement:

Vor dem Objektverhalten "Verschieben"

Ereignis-IDStartdatumEnddatumVon-RouteIDBis-Routen-IDVon-MesswertBis-Messwert

Event1

01.01.2000

<NULL>

Route1

Route3

0

30

Event2

01.01.2000

<NULL>

Route3

Route4

30

48

Nach dem Objektverhalten "Verschieben"

The following diagram provides details about the route after retirement:

Nach dem Objektverhalten "Verschieben"

Ereignis-IDStartdatumEnddatumVon-RouteIDBis-Routen-IDVon-MesswertBis-MesswertPositionsfehler

Event1

01.01.2000

01.01.2005

Route1

Route3

0

30

Kein Fehler

Event1

01.01.2005

<NULL>

Route1

Route3

0

30

Teilweise Übereinstimmung für den Bis-Messwert

Event2

01.01.2000

01.01.2005

Route3

Route4

30

48

Kein Fehler

Event2

01.01.2005

<NULL>

Route3

Route4

30

48

Teilweise Übereinstimmung für den Von-Messwert

Verhalten "Stilllegen"

Die Routen sind ab dem 1.1.2000 aktiv. Wenn die Stilllegung auf den 1.1.2005 festgelegt ist und Route nachgelagert neu kalibrieren deaktiviert ist, hat dies folgende Auswirkungen:

  • Objekt1 wird stillgelegt, da es sich innerhalb der stillgelegten Region befindet.
  • Objekt2 wird stillgelegt, da es sich innerhalb der stillgelegten Region befindet.

Vor dem Objektverhalten "Stilllegen"

The following table provides details about the events before retirement:

Nach dem Objektverhalten "Stilllegen"

Ereignis-IDStartdatumEnddatumVon-RouteIDBis-Routen-IDVon-MesswertBis-Messwert

Event1

01.01.2000

<NULL>

Route1

Route3

0

30

Event2

01.01.2000

<NULL>

Route3

Route4

30

48

Nach dem Objektverhalten "Stilllegen"

The following diagram provides details about the route after retirement:

Anhand des Diagramms und der Tabelle unten wird deutlich, dass beide Objekte stillgelegt wurden und kein Datensatz in der Attributtabelle vorhanden ist.

Nach dem Objektverhalten "Stilllegen"

Ereignis-IDStartdatumEnddatumVon-RouteIDBis-Routen-IDVon-MesswertBis-MesswertPositionsfehler

Event1

01.01.2000

01.01.2005

Route1

Route3

0

30

Kein Fehler

Event2

01.01.2000

01.01.2005

Route3

Route4

30

48

Kein Fehler